
 |
|
Joints in Concrete Slabs on a Grade -- What, why, & how?
|
|
|
WHAT are joints
Concrete expands and shrinks with changes in moisture
and temperature. The overall tendency is to shrink
and this can cause cracking at an early age. Irregular
cracks are unsightly and difficult to maintain but generally
do not affect the integrity of concrete. Joints
are simply pre-planned cracks. Joints in concrete slabs
can be created by forming, tooling, sawing, and placement
of joint formers.
Some forms of joints are:
- Contraction joints – are intended to create weakened
planes in the concrete and regulate the location
where cracks, resulting from dimensional
changes, will occur.
- Isolation or expansion joints – separate or isolate
slabs from other parts of the structure, such as walls,
footings, or columns; and driveways and patios
from sidewalks, garage slabs, stairs, lightpoles and
other points of restraint. They permit independent
vertical and horizontal movement between adjoining
parts of the structure and help minimize cracking
when such movements are restrained.
- Construction joints – are surfaces where two successive
placements of concrete meet. They are typically
placed at the end of a day’s work but may be
required when concrete placement is stopped for
longer than the initial setting time of concrete. In
slabs they may be designed to permit movement
and/or to transfer load. The location of construction
joints should be planned. It may be desirable
to achieve bond and continue reinforcement
through a construction joint.
|

|
|
|
WHY are Joints Constructed
Cracks in concrete cannot be prevented entirely, but
they can be controlled and minimized by properly designed
joints. Concrete cracks because:
- Concrete is weak in tension and, therefore, if its
natural tendency to shrink is restrained, tensile
stresses that exceed its tensile strength can develop,
resulting in cracking.
- At early ages, before the concrete dries out, most
cracking is caused by temperature changes or by
the slight contraction that takes place as the concrete
sets and hardens. Later, as the concrete dries,
it will shrink further and either additional cracks
may form or preexisting cracks may become wider.
Joints provide relief from the tensile stresses, are easy
to maintain and are less objectionable than uncontrolled
or irregular cracks.
HOW to Construct Joints
Joints must be carefully designed and properly constructed
if uncontrolled cracking of concrete flatwork
is to be avoided. The following recommended practices
should be observed:
- The maximum joint spacing should be 24 to 36
times the thickness of the slab. For example, in a
4-inch [100 mm] thick slab the joint spacing should
be about 10 feet [3 m]. It is further recommended
that joint spacing be limited to a maximum of 15
feet [4.5 m].
- All panels should be square or nearly so. The length
should not exceed 1.5 times the width. Avoid
L-shaped panels.
- For contraction joints, the joint groove should have
a minimum depth of 1/4 the thickness of the slab,
but not less than 1 inch [25 mm]. Timing of jointing
operations depends on the method used:
- Preformed plastic or hard board joint strips are
inserted into the concrete surface to the required
depth before finishing.
- Tooled joints must be run early in the finishing
process and rerun later to ensure groove bond
has not occurred.
- Early-entry dry-cut joints are generally run 1 to
4 hours after completion of finishing, depending
on the concrete’s setting characteristics.
These joints are typically not as deep as those
obtained by the conventional saw-cut process,
but should be a minimum of 1 inch [25 mm] in
depth.
- Conventional saw-cut joints should be run
within 4 to 12 hours after the concrete has
been finished.
- Raveling during saw cutting is affected by the
strength of the concrete and aggregate characteristics.
If the joint edges ravel during sawing, it
must be delayed. However, if delayed too long,
sawing can become difficult and uncontrolled
cracking may occur.
- Use premolded joint filler such as asphalt-impregnated
fiber sheeting, compressible foam strips, or
similar materials for isolation joints to separate slabs
from building walls or footings. At least 2 inches
[50 mm] of sand over the top of a footing will also
prevent bond to the footing.
- To isolate columns from slabs, form circular or
square openings, which will not be filled until after
the floor has hardened. Slab contraction joints
should intersect at the openings for columns. If
square openings are used around columns, the
square should be turned at 45 degrees so the contraction
joints intersect at the diagonals of the
square.
- If the slab contains wire mesh, cut out alternate
wires, or preferably discontinue the mesh, across
contraction joints. Note that wire mesh will not prevent
cracking. Mesh tends to keep the cracks and
joints tightly closed.
- Construction joints key the two edges of the slab
together either to provide transfer of loads or to
help prevent curling or warping of the two adjacent
edges. Galvanized metal keys are sometimes
used for interior slabs, however, a beveled
1 by 2 inch [25 by 50 mm] strip, nailed to bulkheads
or form boards, can be used in slabs that are
at least 5 inches [125 mm] thick to form a key which
will resist vertical loads and movements. Keyed
joints are not recommended for industrial floors.
Metal dowels should be used in slabs that will carry
heavy loads. Dowels must be carefully lined up and
parallel or they may induce restraint and cause random
cracking at the end of the dowel.
- Joints in industrial floors subject to heavy traffic
require special attention to avoid spalling of joint
edges. Such joints should be filled with a material
capable of supporting joint edges. Manufacturer’s
recommendations and performance records should
be checked before use.
|
|
Follow These Rules to Prevent Crazing
- Use moderate slump (3-5 inches) concrete with reduced bleeding characteristics.
- Follow recommended practices and timing, based on concrete setting characteristics, for placing and
finishing operations:
- Avoid excessive manipulation of the surface, which can depress the coarse aggregate, increase the
cement paste at the surface, or increase the water-cement ratio at the surface.
- DO NOT finish concrete before the concrete has completed bleeding. DO NOT dust any cement onto the
surface to absorb bleed water. DO NOT sprinkle water on the surface while finishing concrete.
- When steel troweling is required, delay it until the water sheen has disappeared from the surface.
- Cure properly as soon as finishing has been completed.
|
|
|
References
- Joints in Concrete Construction, ACI 224.3R,
American Concrete Institute, Farmington Hills, MI.
- Guide for Concrete Floor and Slab Construction, ACI 302.1R,
American Concrete Institute, Farmington Hills, MI.
- Slabs on Grade, ACI Concrete Craftsman Series CCS-1
American Concrete Institute, Farmington Hills, MI.
- Joint Planning Primer, Concrete Construction
- Ward Malisch,Avoiding Common Outdoor Flatwork Problems, August 1997.
- Bruce A. Suprenant,Sawcutting Joints in Concrete,
Concrete Construction, January 1995.
|
|
|
Back to Tip Index |
|
|
USED WITH PERMISSION FROM THE NRMCA |
|
|